Validation programme

Every number this tool produces, validated against published engineering data.

Nineteen case studies run the engine against published feasibility studies, measured network data, published scheme design parameters and national benchmark surveys. Where the engine and the reference disagreed, the difference was either explained or fixed in the product. Both outcomes are on this page, including the cases where the tool was wrong.

Arup Basingstoke 2019 OpenDHN Verbier Aalborg smart meters BEIS network survey

Every benchmark below is a permanent test file in the codebase, so each result is reproducible rather than a one-off claim.

19
Case studies
1,842
Passing tests
9,622
Buildings, largest run
16
Defects surfaced
11
Of those, fixed
3 yr
Measured hourly data

Test count as at 2 October 2026: 1,842 passing, 5 skipped, 0 failures, 126 files.

Published references not internal examples
Measured data where measured data exists
Failures published alongside the passes
The standard being applied

A design tool is only worth what its worst assumption is worth.

Most heat network software asks to be trusted on the strength of a feature list. That is not a reasonable ask of anyone signing their name to a feasibility study. So the engine is run against work that has already been published and peer-reviewed by the market, and the comparison is put here whichever way it goes.

Published, not synthetic

References are real: a consultant's issued pipe schedule, a measured Swiss network, three years of Danish smart meter data, a BEIS survey of seven operating UK networks. No self-generated test case counts as validation.

Reproducible, not asserted

Each case is a permanent vitest file, not a screenshot in a PDF. If a future change breaks a benchmark, the test suite fails before the claim on this page becomes false.

Provenance-tiered

Every engineering figure in the product carries a tier: a quoted standards clause, a named source, a labelled rule of thumb, or a placeholder. A rule of thumb is never presented as a standards clause.

Disagreements published

Sixteen findings came out of this programme, most of them defects in our own engine. Eleven are fixed. The rest are listed below with their current status.

The results

Nineteen case studies.

Scale runs from a 19-building scheme with a published pipe-by-pipe schedule up to 9,622 real building footprints across 402 km of routed main, and out to standalone district cooling, true 4-pipe heating-and-cooling, and the DESNZ zoning appraisal run building by building at London density. Case studies 16 to 19 re-run published schemes end to end: a feasibility study, a zone opportunity, an operating network and a data centre heat network in Ireland.

# Case study Scale What is validated Result
01 Basingstoke NHH
Arup, 2019, published feasibility
19 buildings
5.8 MW · 1,969 m
Pipe sizing, installed cost, auto-routing Agrees 39 of 41 segments within one DN on the app's own default sizing window, 20 exact, rising to 29 exact on the wider window a consultant would work to. The two that differ by more than one size are Arup's deliberately future-proofed DN200 spine, running at 0.30 to 0.32 m/s at design load which appears to reflect deliberate future-proofing for town-centre expansion rather than current peak demand, so a purely demand-driven sizing algorithm would not be expected to reproduce it; the tool flags both as below the 0.5 m/s floor rather than accepting them silently. All 19 building loads match Arup's own assumptions table exactly (5,980 kW, 19,591 MWh/yr). Auto-routed mains within 11% of the as-built route, from public OpenStreetMap roads alone. Network capex lands within 0.3% of the published total, but the civils rates were calibrated to this same schedule, so that one is a calibration check rather than an independent one.
02 Verbier, Switzerland
OpenDHN, Zenodo, measured
150 substations
681 pipes · 12 km
EN 13941 heat loss against a measured energy balance Agrees Engine 253 to 275 kW against 317.6 kW measured, or 7.0 to 7.7% of generation against 8.85% measured. Flow 21.5 l/s computed against 22.8 kg/s measured, roughly 3% on a temperature-basis difference.
03 Aalborg, Denmark
3,021 smart meters, measured
3,021 dwellings
3 years hourly
Domestic demand profiles and diversity Agrees Measured diversity plateaus at 0.49. The CIBSE CP1 and Varme Ståbi default of 0.62 is confirmed conservative-safe rather than accurate, which is the useful finding.
04 BEIS UK survey
7 operating UK networks
Population study Heat loss per metre, cost norms, CP1 limits Agrees Engine sits at the as-new edge of the measured band, which is the correct place for design-stage physics with no ageing or joint losses modelled.
05 Basingstoke techno-economics
Arup, 2019, Table 3.9.1
10 financial scenarios NPV and IRR discounting mathematics Agrees NPV exact on all ten scenarios to a £1 tolerance. IRR within 0.55 percentage points at 40 years once the cash-flow ramp-up is accounted for.
06 South Basingstoke city-scale
Real OpenStreetMap footprints
4,090 buildings
7,660 pipes · 157 km
Auto-routing and sizing at city scale Found defects Routing 1.3 s, analysis 0.1 s, 0 of 4,090 unreachable. Exposed the findBestDN null-fallback affecting 54% of all pipes, and materials-only capex. Both fixed and re-verified.
07 Mijnwater Heerlen
Netherlands, operating 5GDHC
20,000 m² cluster
real ambient loop
Cooling energy balance and dominant-season sizing Found a defect Recovers 1,000 MWh/yr of cooling into heating, net +800 MWh/yr on the mine store, COP inside the measured SCOP 3 to 5 band. Surfaced that the engine sized on the heating peak even when reporting cooling as dominant. Fixed.
08 Southampton DES
UK, operating since 1986
11 km mains
40 GWh/yr
Linear heat density against the UK's longest-running multi-source network Challenges the reference A scheme that has operated for 40 years sits at 3.6 MWh/m/yr, below the BEIS bulk-scheme band of 5.9 to 18.3. That band is a bulk-scheme norm, not a viability floor, and should not be used as a screening cut-off.
09 Nottingham Enviroenergy
Eastcroft EfW-CHP
68 km mains
150 GWh/yr
Gas counterfactual and EfW-CHP carbon factor Agrees The tool's counterfactual matches Nottingham's own published gas comparator to within 1%. Also confirmed that a generic waste heat recovery factor of 5 gCO₂e/kWh is not a valid stand-in for EfW-CHP and understates it by more than tenfold.
10 GIS import at city scale
Real OSM footprints
9,622 footprints
3.12 Mm² floor area
Property mapping, centroid and area derivation, demand fallbacks Found defects Found that 95.8% of buildings imported at zero annual demand and 100% at zero peak, so every pipe sized at 0 kW. Both fixed. Mapping now completes in about 50 ms and yields 296 GWh/yr at 94.8 kWh/m²/yr.
11 Basingstoke mega-scale
Real OSM, engine ceiling test
9,622 buildings
18,147 pipes · 402 km · 195.6 MW
The full import, route, size and cost workflow at 2.35x case study 6 Found the ceiling Engine holds: 0 unreachable, routing 2.7 s, analysis 0.53 s. Found the real ceiling, a DN300 catalogue limit that sized a 94.5 MW trunk at 16.1 m/s and 355 bar. Catalogue extended to DN1200; now 0 over-capacity pipes at 2.94 m/s and 31 bar.
12 King's Cross district cooling
Published scheme design basis
12.5 MW cooling
9 MW chiller plant
Standalone chilled-water sizing and electric-chiller plant energy Agrees on design basis Sizing and plant match King's Cross's published design parameters. What is not published is stated plainly: annual cooling energy and plant electricity are a labelled illustrative reconstruction, not metered figures.
13 King's Cross full DHC
Operating 4-pipe estate
Heating + cooling
one shared trench
4-pipe DHC sizing over a shared topology and the shared-trench synergy Agrees on design basis Sizes heating and cooling over one shared trench and quantifies the synergy that defines a true DHC scheme. The cooling side is validated against published plant; the heating-side annual energy is illustrative.
14 Zone-boundary refinement
DESNZ zoning method
Worked example
per-building appraisal
Per-building linear heat density and the network-vs-individual-ASHP zoning appraisal Method validated The per-building appraisal, exclusion prune and resize-on-apply reproduce the DESNZ zoning method on the HMT Green Book basis. The building demands are an illustrative worked example, not a published scheme.
15 City-scale zoning, London density
Real OSM footprints
1,000 buildings
53 km · 2.4 km²
The DESNZ zoning appraisal end to end through the real router and sizing Performance and plausibility Runs the full building-by-building zoning appraisal over 1,000 buildings in about 30 ms, at a plausible 2.67 MWh/m/yr. In the same class as case study 6: a scale and performance test, not an accuracy claim.
16 Bromsgrove feasibility study
Greenfield for Bromsgrove DC, 2019
68 consumers
19.3 GWh/yr · 10.1 km
A published feasibility study re-run end to end: route, sizing, heat loss and plant dispatch Agrees Demand 19,335 against 19,334 MWh/yr and heat loss 10.1% against 11%; the plant meets every hour with the report's heat pump, CHP and boilers. Diversity, route length and cost rates differ by method and are set out in the case study.
17 Southampton Highfield zone opportunity
AECOM for Southampton CC, DESNZ zoning pilot, 2025
10 loads
20.9 GWh/yr · 4.3 km
A published zone opportunity appraised building by building Agrees on design basis Network length 4.3 km against more than 4 km. The campus network beats individual heat pumps by 13%; five small sites do not, and dropping them leaves 1.15 km at 16.7 MWh/m/yr.
18 Nottingham estate network
Tunzi et al., Energy and Buildings, 2017
7 buildings
594 m · 374 MWh/yr
Lowering the return temperature of an operating network, against a TERMIS model Agrees Flow falls to 0.374 of the original against 0.383, and heat loss by 9.7% against 8.5%. Design loss 7.5 kW against 7.75 kW from the paper's own pipe data.
19 Tallaght District Heating Scheme
Heat Works / South Dublin CC, data centre heat, 2023
6 substations
3 MW heat pumps · 1.7 km
A network on recovered data centre heat, under the Irish and European settings Agrees on design basis Routed trench 1.73 km against 1.9 km, sizes DN50 to DN150 against DN65 to DN200, and the 3 MW heat pumps meet every hour. Heat loss comes out below the reported 15%, as an as-new design value.

Chips reflect the comparison outcome, not a marketing grade. "Found defects" means the case study did its job.

What it got wrong

The findings that mattered most were failures.

Sixteen findings came out of this programme. Eleven are fixed and merged, one is in progress, three remain open and one turned out to be a real working limit rather than a defect. The four below are the ones that would have changed an answer given to a client.

01

54% of pipes silently sized to DN50

What happened. Where no catalogue size satisfied both the velocity window and the pressure-gradient floor, findBestDN fell back to DN50 without saying so. On a real 7,660-pipe city network that hit 4,145 pipes, including a 23.4 MW main forced to DN50, which produced a computed pump head of 25 GPa.

Why it survived. Every smaller test network had a valid solution for every pipe, so the fallback path was never taken. Only real city-scale geometry reached it.

Fixed and merged Graceful degradation via findBestDNDetailed, which reports the mode it had to use. Pump head on the same network dropped to 5,044 kPa and the null-fallback count to zero.

02

Capex was eight times too low

What happened. Default pipe rates were materials-only, roughly 8x below installed cost. Any capex figure the tool produced was a lower bound presented as an estimate.

Why it matters. This is the number a business case turns on, and being wrong in the optimistic direction is the worst way to be wrong.

Fixed and merged A pipe supply and civils split calibrated against the Arup schedule to within 0.3%. Case study 6's capex moved from a £35.5m materials-only lower bound to £341m on the same network.

03

Imported buildings arrived with no demand

What happened. The non-domestic TM46 benchmark returned nothing for domestic buildings, and nothing derived a missing peak from an annual figure. Importing 9,622 real footprints gave 95.8% zero annual demand and 100% zero peak, so the engine sized every pipe at 0 kW.

Why it survived. The DECC per-dwelling archetype benchmarks that exist to fill exactly this gap were wired into the case-study scripts but never into the import path a user actually uses.

Fixed Domestic now falls back to the DECC archetype, reading built form, age band and dwelling count from the file where present and recording the assumption on the node so it is visible and editable rather than silent.

04

Two shipped projects claimed terawatt-hours of heat

What happened. Two case-study generators wrote kWh/yr into a field defined as MWh/yr. The shipped project files claimed 19.6 TWh and 79.4 TWh of annual heat.

Why it survived. Each generator's own summary divided by 1000 a second time, so the results stayed internally consistent. The summary was right while the file a user would actually load was 1000x out. No pinned-number test would have caught it.

Fixed Generators corrected, both project files regenerated, and every shipped project is now guarded dimensionally: annual and peak must imply a physically possible full-load-equivalent hours figure.

Still open

  • Interactive building discovery caps at 3 km² per query. Case study 6 confirmed this is empirically necessary, since a single larger query times out against the public Overpass server, rather than a conservative safety margin.
Scope and limitations

What this tool is not.

HeatNet Designer is a feasibility and concept design platform, aimed at roughly RIBA stages 0 to 3. That boundary is deliberate. These are the limits worth knowing before you rely on an output.

Steady-state, not transient

Every hydraulic result is a snapshot at a design condition. There is no transient thermal propagation and no dynamic control response. Surge is a discrete Joukowsky check, not a full transient solve.

Cost rate provenance is mixed

Civils are calibrated to DECC 2015 (URN 15D/022) and the Arup Basingstoke feasibility study, and HIU cost per dwelling comes from DECC 2015 Table 8. Pipe supply rates are indicative materials-only figures, and pump and valve rates are explicit placeholders, because those are trade-quote only across UK suppliers. Every rate is editable and the report prints the basis of each one. Substitute your own before relying on a cost output: directionally useful, not tender-grade.

On a ring, flows are solved and node pressures are not

A Hardy-Cross solver balances looped topologies and closes all seven real loops in Verbier's genuine two-plant mesh. Two limits follow. Cumulative pressure is then re-accumulated along a spanning tree, so the differential pressure reported at a substation on a ring is approximate rather than a solved nodal pressure. And on a mesh as complex as Verbier the solver does not tighten below its 1e-6 m³/s tolerance within its 100-iteration budget, which the Analysis tab flags. Neither is an inability to represent a mesh; a nodal pressure solver is the current work.

Perfect-foresight storage dispatch

The optimiser assumes the controller knows the whole year in advance. This is the standard feasibility-stage assumption and the same one energyPRO makes, but it brackets the value of a thermal store from above. A real controller on a day-ahead forecast captures most, not all, of the modelled saving.

Plastic pipe catalogue is a stub

The EN 15632 plastic flexible twin-pipe physics is verified, but the catalogue numbers are representative placeholders pending certified manufacturer data. The EN 253 steel catalogue uses the LOGSTOR 2025 product tables: DN20 to DN500 in all three insulation series and DN20 to DN1200 in series 1. The few larger series 2 and 3 casings the catalogue lists only on enquiry are extrapolated and flagged in the code.

Four of eight compliance checks are document-backed

Velocity, the TS1 distribution heat-loss check and pump redundancy cite a clause, and the linear heat density target is the DESNZ zoning design threshold. The other four are HeatNet design defaults, labelled as such in the product. CIBSE CP1:2020 contains no Pa/m pressure-gradient limit, no matter how many tools imply one.

UK-focused

Benchmarks, carbon factors, the cost library and the standards set are UK-centric. Prices are converted between currencies at the ECB reference rate, which re-expresses UK and Danish rates rather than replacing them with local prices.

DHW diversity uses a proxy

Domestic hot water diversity uses a 1/√N simultaneous-use proxy, not the fixture-unit method of BS EN 806-3.

Method

How each case study is run.

1

Take published or measured inputs

Demands, temperatures and pipe geometry come from the reference document or dataset, not from our own assumptions. Nothing is tuned to make the comparison flattering.

2

Run them through the engine's public API, or the app itself

The same code path a user gets. In-app reports are generated by the software's own Report tab print pipeline with no manual editing.

3

Compare quantity by quantity

Not a headline total. Case study 1 compares all 41 individual pipe segments against the issued schedule; case study 5 compares all ten financial scenarios.

4

Diagnose every disagreement

Each difference is either explained as an assumption rather than a physics error, or fixed in the product. Both outcomes are recorded, including the sixteen findings above.

5

Pin it as a permanent test

Each benchmark becomes a vitest file in the suite, so a future change that breaks the result fails the build rather than quietly invalidating this page.

Check it yourself

Bring a scheme you already know the answer to.

The fastest way to judge this is to run something you have already designed and see whether the engine agrees with you. Open the designer and load one of the validated case studies, or send a scheme and we will run it and send the output back.

Free to try, sign in with your email. Up to 500 buildings and 2 saved projects; enterprise and city-scale on request.

HeatNet Designer · UK Edition Overview Product tour Privacy Terms Support Contact For preliminary design. Figures on this page are traceable to the validation case studies in the codebase.